Projectlab controlled a strict programme to deliver a new workplace for advertising agency Anomoly.

The agency was relocating to a larger space to accommodate their growing numbers and a more flexible style of working. We co-ordinated a restricted programme to ensure all elements of the fit-out were executed to enable use of the same contractor working on a downstairs property. Working in conjunction with the design team we were able to reduce the project spend through the reuse of existing workstations and strategic design interventions.

Size
4000sqft

Time
5 weeks

Services
Project Management

Aqueduct

Projectlab delivered this office space for creative agency Aqueduct within very limited cost and time constraints. Relocating to an upper floor of Smithfield Market, the historic nature of the building posed a number of challenges including possible risk of Asbestos contamination. Budget constraints were managed by streamlining the scope, with smart selection of easily procurable finishes and joinery items designed to be constructed off site and retrofitted. Programme challenges overcome included coordinating landlord management teams and sequencing building system alterations.

Size
7000sqft

Time
6 weeks

Services
Project Management

 

Threepipe

Projectlab delivered this maximum impact project with limited budget and timescales for new creative agency Threepipe. The merge of two companies, Blowfish Digital and Threepipe, required their relocation to new office premises to accommodate all staff. Fast track delivery was required prior to the expiry of leases at their existing offices. A key challenge was maximising the budget to deliver impact. We created pockets of 'wow' within the new office space while leaving other areas raw and unfinished.

Size
3,100sqft

Time
4 weeks

Services
Project Management
Contract Administration
Cost Control
CDMC

33 Boundary Street

Projectlab's offices are located in the heart of Shoreditch in the East End of London occupying the ground floor of a converted warehouse building.

The office space is a hot bed of activity and a display window to the world of the work and talent which emerges from within. The open plan workspace, integrated discussion areas and collaborative zones allow innovation, thinking, learning and design to simultaneously happen providing a holistic approach to clients which is both reasoned and inspired.

Size
1,200 sq ft

Time
6 weeks

Services
Project Management

Emap Communications

Projectlab delivered the comprehensive refurbishment of 60,000 sq ft of office space for media group Emap, within this landmark building in north London.

The project entailed extensive coordination to manage multiple trades and consultants across a several phased programme. We worked closely with the QS to achieve maximum value from a tight budget. Close collaboration with the building management team helped to enable the smooth execution of the project.

Size
100,000 sq ft

Time
40 weeks

Services
Project Management

Archant Ilford

Following the demolition of existing print works, Projectlab delivered a new home for publishers Archant on a site in Ilford. The purpose built office building provides a new home for Archant, offering open plan workspace and street presence. The scheme incorporates a signature structural steel frame and high tech glazing system, which entailed full coordination with the structural engineer and specialist consultants.

We achieved delivery of this project within time and budget constraints, despite facing a major hurdle when the contractor fell into administration during the build. We were proactive in securing another company to complete the scheme with minimal disruption to the programme.

Size
16,000sqft

Time
36 weeks

Services
Project Management

Bauer Media

Projectlab delivered this impressive 60,000sq ft office space for Bauer Media on time and within budget. We managed an intensive 16 week schedule, co-ordinating numerous sub-contractors, to achieve this £1.6m fit out. The scheme incorporates atrium-facing cantilever frame meeting rooms which required careful consideration and risk control. 

Size
51,500sqft

Time
24 weeks

Services
Project Management

COI

Projectlab overcame a range of obstacles to deliver this 10,000sq ft office space for government organisation COI. Within a limited 8 week programme we co-ordinated a schedule of works incorporating the extensive removal of asbestos and a complex audio visual package. The scheme was delivered on time and on budget and resulted in repeat commissions from the organisation.

Size
4,500

Time
8 weeks

Services
Project Management